Hi,
U can do one more thing
1) create a general cost activity under WBS element and in that activity u can see a calculator button besides the field amount. clcking on that it will take u to unit costing.
2) do the unit costing there and save it .
3) run report S_ALR_87013542 u can see cost element wise report.
Regards